top of page

Elcon Solar's Commercial Solar Installations;

 

Commercial solar covers a wide variety of business and none for profit organisations. The main advantage to this group is that most of them occupy the properties primarily during sunlight hours when the sun is shining and have very low use after dark therefore the savings and return on investment can be substantial and very worthwhile. As the cost of power never seems to decrease, more and more businesses are deciding to go solar, and why wouldn't you? When you can save approximently 50% - 90% on you energy usage during buissiness hours with a properly designed solar system.

 

Is Solar right for your Business?

 

Any company with a large roof space can recap the rewards of installing a commercial solar system in Melbourne. Elcon Solar offers a variety of site-specific solar panels for businesses of all sizes. These include rooftop panels for collecting solar energy, ground mounted collectors, and a battery system to store excess energy. Our sales consulation can look at your energy usage history and the equipment currently operating within your business which contributes to your bill. They can then discuss how your business can reduce energy consumption and the operating costs associated with the energy demands of your business. 

 

Below is some of our solar installs on our commercial solar projects and click the link below to go to our photo gallery​.

Mega Freight Tullamarine 
99kw Installation

This Commercial Install was at Mega Freight in Tullamarine which was installed by Elcon Solar Pty Ltd and it was a very challenging installation due to lack of space, as you can see we used pretty much the whole roof to install the panels.

 

The installation consisted of the following;

  • 302x 330w Jinko 72 cell Panels 

  • 4x Fronius Eco Inverters

 

We required a forklift and scissor lift to be onsite to help the team get everything onto the roof safely and affectively.

 

The estimated annual output would be 140,000kwhr per annual with an annual saving on the customers electricity bill been roughly $30,000.00

Egg Farm
Terang 
99kw Installation

This Commercial Install was at Casaccio Egg Farm in Terang which was installed by Elcon Solar Pty Ltd and it was by far the easiest big commercial job we have ever installed. 

 

The installation consisted of the following;

  • 304x 325w Jinko 72 cell Panels 

  • 4x Fronuis Eco Inverters 

 

We required a forklift and scissor lift to be onsite to help the team get everything onto the roof safely and affectively.

 

The estimated annual output would be 140,000kwhr per annual with an annual saving on the customers electricity bill been roughly $30,000.00

 

Mushroom Farm 
Ballarat 
30kw Installation
Strawberry Point
Forest Hill 
50kw Installation

This Commercial Install was at Ballarat Mushroom Farm in Ballarat which was installed by Elcon Solar Pty Ltd and was another challenging installation.

 

The installation consisted of the following;

  • 100x 280 Jinko Panels

  • 4x 6kw Fronuis Primo Inverters with smart meter for export control

 

This install was a challenging one as we had to install 44 panels landscape profile running edge to edge on the warehouse. Install 56 panels on custom made tilts mounted through 100mm foam refrigeration sheets on the farm rooms roof.

 

This Commercial Install was at Strawberry Point in Forest Hill which was installed by Elcon Solar Pty Ltd and it was an interesting installation, with a few design challenges. 

 

The installation consisted of the following;

  • 186x 270w Solar Modules Panels 

  • 2x 25kw Fronuis Eco Inverters 

 

This install was challenging with the fact we needed to leave enough space between and above the modules for future whirly birds been installed. We also had to avoid the shade from 1 very big tree which couldnt be removed. The we had to make sure to leave enough room on the roof to expand the solar system in the future.

 

202153623_5719861444753653_1207296449145571337_n.jpg
Mercure Hotel & Conference Centre
Ballarat 
200kw Installation
189646202_5547763195296813_6681564981386361559_n.jpg
Lalor Gardens Primary School 
Lalor 
100kw Installation

This Commercial Install was at Mercure Hotel & Conference Centre in Ballarat which was installed by Elcon Solar Pty Ltd and was another challenging installation.

 

The installation consisted of the following;

  • 540x 370 Trina Solar Panels

  • 2x 100kw SMA Inverters

 

This install was a challenging one as we had to install all panels over two separate buildings and multiple roof faces.

 

This Commercial Install was at Lalor Gardens Primary School in Lalor which was installed by Elcon Solar Pty Ltd 

 

The installation consisted of the following;

  • 190x 370w Canadian Panels

  • 1x SMA 3phase Inverter - 2 Core

 

This install was original 30kw solar system which we upgraded to 100kw. We had to install all panels over separate buildings and multiple roof faces.

 

Elcon Solar Accreditations